  Barrett Parkway at Cobb Place Blvd 

Current Status
as of July, 2011

Project Description: The project includes dual left turn lanes in all four directions, an exclusive
right turn lane for Cobb Place Boulevard southbound to Barrett Parkway eastbound and signal
modifications to the existing traffic signal to accommodate the reconfiguration of lanes.

Project Schedule: Construction began mid summer 2007 and was completed late 2008.

Project Value:
Task Amount/Funding Source

Design: $103,480/Town Center Area CID
Right-of-Way Acquisition: $666,297 - CCDOT
Construction: $2,069,204 – Town Center Area CID; $545,410 – Georgia DOT

Project Team:

Consultant: ARCADIS
Contractor: Butch Thompson Enterprises
Project Sponsor: Town Center Area CID/CCDOT/GDOT


For more information, write TCACID@TCACID.com

 

 

 
 
 


 

Back to the Top    Home
©1999-2012 Town Center Area Community Improvement District 

Disclaimer: The Town Center Area Community Improvement District makes no warranties of any kind, express, implied, or statutory concerning the information provided on this web site. The TCACID accepts no responsibility nor liability for any loss or damages for the information or advice provided at this web site or incorporated into this web site by any reference, or which is incurred as a result of the use or misuse of, or reliance upon, the information and advice contained at this web site. All projects are recommended and not final.